St. Mary's Church- Bell Tower & Water
Proofing renovation work. |
 |
|
INTRODUCTION |
 |
|
St.Mary's Church is an imposing landmark and
a magnificent sight on Sarojini Devi Road, |
 |
|
Secunderabad. It was popularly known as St.
Mary's Cathedral while it was the principle Church of |
 |
|
the vicariate of Hyderabad. |
 |
|
From 1500 till 1832 the vicariate of Hyderabad had small
pockets of Christians who were visited at |
 |
|
regular intervals by missionaries of the Theatine order of
the Carmelite fathers. A significant and |
 |
|
concerted effect at evangelization begun in 1838 when
Fr.Daniel Murphy, an Irish by birth, opted to |
 |
|
work in Hyderabad. The Irish regiment of the British Army
compromised of Catholics while the other |
 |
|
regiments were mostly Anglicans. |
|
|
It was commissioned in 1840 and against many odds, both
financial and personal, the edifice was |
| completed and blessed in 1850. At that time it
was the largest Church in the Kingdom of the Nizams |
| |
| PRESENT CONDITION OF THE
EDIFICE |
| For the last 158 years the Church has enjoyed a
glorious past. But over the years the edifice has been subjected
to severe wear & |
| tear. Even a cursory glance at the structure is
enough to say that urgent repairs have to be carried out so that
the pristine beauty of |
| the Church is maintained. |
|
|
| |
|
|
|
|
| |
|
|
| SITE REPORT |
|
|
| Though numerous suggestions were received from
various quarters, an expert's opinion was essential. Thus L & T
( Larsen & |
| Turbo, Powai Mumbai) were requested to
present a site report and suggested methodology of repair and
renovation. |
| Our team of Mr. Venkateswarlu(architect)
and Mr. Rasool(surveyor) visited the St. Mary's church on 5th
December of 2007 and |
| made the following observations. |
| Suggested Methodology of Repairs
: |
| 1. Bell Tower--Level 04 & 05 |
| Strengthen the existing walls with Grouting
ejection where ever required-and all inner side wall plastering. |
| Fix the Rolla deck sheet at short span with
anchor bolts in to existing slab. |
| Fix the steel plate as shown in drawing section
'AA' with anchor bolts in to existing walls. |
| Remove the existing roof and existing support
timber beams without disturbing the existing parapet and walls |
| Lay the slab and beams as per design. |
| |
|
|
| 2. Roof Top water Proofing |
| All water proofing membrane to be removed. |
| Remove and replace damaged tiles/patches where
concrete has been damaged. |
| In bone dry conditions lay water proof membrane
to manufacturer's spec. |
| Apply aluminium paint over membrane(to
manufacturer's spec). |
| Make sure they all drain properly. |
| |
|
|
| 3. Walls Water Proofing |
| Make the Grouting Ejection and plastering
dampned effected wall. |
| |
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
| |
|
|
| AREA STATEMENT |
|
|
| The total area of Bell Tower--Level 04 &
05---50.00Sq.m |
| The Total of Water Proofing slab
area(approx)----650.0Sq.m |
| The Total of Bituminous Sheet
area(approx)----750.0Sq.m |
|
|
|
TOTAL ESTIMATION COST
Rs 39,16,038 |
|
|
|
AN EARNEST APPEAL |
|
In my capacity as Parish Priest, I would like to make a fervent
appeal to all parishioners and well wishers of St. Mary's Church
to
|
|
kindly cooperate with us and donate generously towards this
noble task of enhancing the durability of the edifice, which has
helped |
|
thousands of faithful in the past 158 years to intimately
experience the presence of God the Father in their lives and the
working of
|
|
His Son Jesus through the power of the Holy Spirit. |
|
May God Bless us all. |
|
|